Information on emission reduction

Phuong Anh Group: Miracle of the largest offshore wind power complex in Vietnam

Phuong Anh Group: Miracle of the largest offshore wind power complex in Vietnam

Phuong Anh Group has achieved a miracle in investing, constructing and putting into operation a wind power complex with 2 wind power plants at sea, with a capacity of 150 MW, the largest in Vietnam.

In the middle of a vast and turbulent sea, with a "mountain of work" for a major wind power plant project with the world's leading technology, right at the time of the Covid-19 pandemic, but with the spirit With great determination, in just over 800 days, Phuong Anh Construction and Trading Company Limited (Phuong Anh Group) along with construction contractors, domestic and foreign experts, Vietnamese engineers and workers has made a miracle of investing, building and putting into operation a wind power complex with 2 wind power plants Hoa Binh 1 and Hoa Binh 2 at sea, the largest capacity of 150 MW in Vietnam.

Diary of more than 800 days of miracles

In May 5, Hoa Binh 2019 Wind Power Investment Joint Stock Company and Vietnam Electricity Group in Hanoi signed a power purchase contract.

On June 1, 6, construction started on Hoa Binh 2019 Wind Power Plant Project (Bac Lieu), former Deputy Prime Minister Trinh Dinh Dung attended.

On September 7, 9, geological and topographic survey at sea.

On December 20, 12, a contract to provide wind turbine equipment and services was signed between Hoa Binh 2019 Wind Power Investment Joint Stock Company and Vestas (Denmark).

On December 24, 12, the first test pile was driven at sea.

In April 4, mass construction on the sea began. After 2020 month, May 1, the Project began to take shape.

On June 27, 6, signed a contract to build a super-heavy barge Hoa Binh 2020 (pontoon) with a 1 ton crane/ES.PT-10.000.

On July 26, 7, construction started on Hoa Binh 2020 Project Phase II and Hoa Binh 1 Project.

Investment project of Hoa Binh Wind Power Plant 1, Hoa Binh Wind Power Plant 2 has a total investment capital of more than 8.225 billion VND, total installed capacity of 150 MW, annual electricity output of more than 600 million kWh/year, is the largest offshore wind power complex in Vietnam, bringing high economic efficiency to the locality and country, contributing to affirming the sacred sovereignty of the sea and islands of the Fatherland.

On November 26, 11, the Council of Science - Education and Environment and the Vietnam Chamber of Commerce and Industry (VCCI) awarded the "Typical Vietnam Renewable Energy Project" award to the Housing Project. Hoa Binh 2021 Wind Power Plant and Hoa Binh 1 Wind Power Plant in Bac Lieu province.

July and August 7, speed up construction.

On September 30, 9, the first bridge girder slab was installed at sea.

On October 26, 10, the Hoa Binh 2020 super barge was launched after 1 months of construction.

On November 20, 11, construction of the 2020 KV line.

On February 9, 2, signed PPA contract for Hoa Binh 2020 Phase II and Hoa Binh 1 Project.

On December 12, 12, Hoa Binh 2020 barge was handed over.

On December 21, 12, continued cutting plating to build the second super barge named Hoa Binh 2020 to serve equipment installation.

On March 12, 3, installation of the first turbine at sea began.

On April 2, 4, the first turbine was completed.

On April 4, 4, the 2021 ton super-heavy barge Hoa Binh 10.000 was launched.

On April 5, 4, signed a contract to construct and install 2021 sets of Hoa Binh 26 turbines, phase II and Hoa Binh 1 Project.

On April 27, 4, signed a comprehensive contract between ViettinBank Thanh An Branch and Phuong Anh Group and a credit contract with Hoa Binh 2021 Wind Power Investment Company Limited.

On May 10, 5, phase I bridge was completed.

On June 20, 6, installation of the first 2021 turbines of Hoa Binh 13 project was completed.

On July 2, 7, Hoa Binh 2021 Factory phase I was energized.

On July 6, 7, the first generator set generated power.

On July 11, 7, the furthest turbine was installed (2021 km from Bac Lieu sea dyke) bearing the Vietnamese National Flag, affirming national sovereignty at sea.

On August 5, 8, Hoa Binh 2021 Factory phase II was energized.

On August 19, 8, construction began on turbine installation of Hoa Binh 2021 Project.

On September 15, 9, Hoa Binh 2021 Plant was energized, putting all 2 turbines of Hoa Binh 39 - Hoa Binh 2 Plant into operation to generate electricity before the Government's preferential deadline, opening a new page of the Group. Phuong Anh Group in the field of investment in clean energy production for the Fatherland.

The largest wind power complex in Vietnam

As if by "magic", in just over 800 days, Phuong Anh Group, together with domestic and foreign contractors, experts, a team of Vietnamese engineers and workers, successfully completed the wind power complex project with hundreds of thousands of workers. A series of projects rising from the seabed, typically a 26 km long sea bridge connecting the mainland with the sea; built 2 super heavy barges of 10.000 tons - the 2 largest barges in Vietnam; Construction of Hoa Binh 1 and Hoa Binh 2 Wind Power Plants with 39 offshore wind turbines; executive office project on land..., turning a vast sea area with only waves and wind into a modern record wind power complex on the sea in Vietnam.

The investment project of Hoa Binh Wind Power Plant 1 and Hoa Binh Wind Power Plant 2 has a total investment capital of more than 8.225 billion VND, total installed capacity of 150 MW, annual electricity output of about 600 million kWh/year. This is the largest offshore wind power complex in Vietnam, bringing high economic efficiency to the locality and country, contributing to affirming the sacred sovereignty of the sea and islands of the Fatherland.

Not only that, this is also the first wind power project in Vietnam to carry out all procedures and register directly with Gold Standard (Gold Standard, thereby directly generating GS VER credits).

 

 

By being confirmed as a Gold Standard project, in addition to having an additional revenue source from GS VER credit transactions, the Project is also confirmed to have the highest level of environmental integrity, contributing to in the process of implementing the United Nations Sustainable Development Goals through 3 criteria: SDG7 - SDG 8 and SDG 13. This is also the Group's criterion to aim to be a green business, contributing to implement Vietnam's commitments at COP26.

General Director of Phuong Anh Group, Ms. Hoang Thi Phuong added: "Two wind power plants named Hoa Binh 1 and Hoa Binh 2 provide additional power sources to the national power grid, contributing to ensuring security." energy, using clean energy, minimizing factors that cause environmental pollution, aiming for green growth, sustainable development and responding to climate change in Vietnam. The project contributes to the successful implementation of one of the 5 pillars of socio-economic development of Bac Lieu province, which is "renewable energy (wind power, solar power) and gas power, making Bac Lieu a center national clean energy as set out in the Resolution of the 2020th Provincial Party Congress for the 2025-1 term. Along with that, Hoa Binh XNUMX continues to be invested in to become a new and unique destination that attracts a large number of domestic and foreign visitors and tourists."

According to Investment newspaper

← Previous Post Next article →