Quang Tri Provincial People's Committee approved the policy of investing in 2 wind power plants

[responsivevoice_button rate=”1″ pitch=”1.2″ volume=”0.8″ voice=”Vietnamese Male” buttontext=”Play”]
The People's Committee of Quang Tri province has just decided to approve the investment policy of 2 wind power projects: TNC Quang Tri 1 Wind Power Plant and TNC Quang Tri 2 Wind Power Plant.
Specifically, Decision No. 3445/QD-UBND approved the investment policy for TNC Quang Tri 1 Wind Power Joint Stock Company (addressed at 128A, Hung Vuong Street, Dong Ha City, Quang Tri Province) to implement the project. TNC Quang Tri 1 wind power plant in Tan Thanh commune, Lao Bao special economic and trade zone, Huong Hoa district, Quang Tri province. The project has a capacity of 50MW with an estimated land use area of 22,37 hectares, of which, the land area for term use is 17,37 hectares; Land area for temporary use is 05 hectares. The factory has a total investment of more than 1.805 billion VND. Of which, the capital contributed to implement the project is more than 542 billion VND, the remaining 70% of capital is borrowed from banks. The project completion schedule is 14 months from the approval of the investment policy and the project operation term is 50 years.
At the same time, Decision No. 3422QD-UBND dated December 2, 12 of the People's Committee of Quang Tri province approved the investment policy for TNC Quang Tri 2020 Wind Power Joint Stock Company (addressed at 2A, Hung Vuong Street, Dong Ha City , Quang Tri province) implementing the TNC Quang Tri 128 wind power plant project in Tan Thanh commune and Tan Long commune, in Lao Bao special economic and trade zone, Huong Hoa district, Quang Tri province. The project has a capacity of 2MW with an estimated land use area of 50 hectares. Of which, the land area for fixed-term use is 22,37 hectares; Land area for temporary use is 17,37 hectares.
The factory has a total investment of more than 1.167 billion VND, of which capital contributed to implement the project is more than 500 billion VND, loan capital mobilized from banks is more than 1.667 billion VND. Project completion schedule is 14 months from approval of investment policy. The project's operating term is 50 years...
TNC Quang Tri 1 wind power project and TNC Quang Tri 2 wind power project were approved for investment and construction in communes of Lao Bao special economic and trade zone, Huong Hoa district, Quang Tri province This is a project with a special investment incentive industry, so it enjoys special preferential policies on corporate income tax, import tax, etc.
See more: Bac Lieu has a Kosy wind power plant project with a capacity of 40 MW
According to Nangluongsachvietnam.vn